CDOT ready to roll on $390 million in road projects in metro Denver area

Hamon Contractors is building the middle segment of the new 104th Avenue bridge in Northglenn, replacing an original I-25 bridge from 1962. CDOT photo.

Hamon Contractors is building the middle segment of the new 104th Avenue bridge in Northglenn, replacing an original I-25 bridge from 1962. CDOT photo.

By Kevin Flynn
Inside-Lane.com

More than $390 million in road construction projects on state highways will be underway this year in the metro Denver area, with more than a third of the total funded by the federal stimulus program.

The activity is spread across 32 projects in the Colorado Department of Transportation’s Region 6, which covers much of the Denver area with the exception of Boulder and Douglas County south of Highlands Ranch. It includes projects CDOT is doing plus several city projects in Denver and Aurora on state highways that CDOT is overseeing.

CDOT’s Region 6 staff led by Region Director Reza Akhavan outlined the projects in a briefing that brought to light some of the savings achieved recently in bidding results that allowed budgeted funds to be plowed back into additional work.

“This will be keeping us very busy this year,” Akhavan said.

CDOT aerial photo shows grading work at the 120th Avenue Connection project over US 36, looking southwest.

CDOT aerial photo shows grading work at the 120th Avenue Connection project over US 36, looking southwest.

Foremost was savings in the $23.3 million 120th Avenue Connection project in Broomfield, which is providing a straight-across link west-to-east from CO 128 to 120th Avenue to allow traffic to bypass the busy Wadsworth/Midway Boulevard interchange with U.S. 36. Inside Lane wrote about this project when ground was broken, and at the time, CDOT didn’t have funding to start the second phase that would include the tie-ins on the east side with 120th.

Now, says CDOT Region 6 North Program Engineer John Schwab, savings achieved through the design-build contracting process used by CDOT and the contractor partnership of Edward Kraemer & Sons and HNTB will allow CDOT to begin design work on that second phase, as well as right-of-way acquisition. The hefty construction costs for that phase, estimated up to $40 million, means the rest will have to wait for more funding.

They projects range from the inexpensive– such as a $180,000 paint restriping of Parker Road between Hampden and Belleview Avenues to fit in third lanes in each direction, a small price to squeeze out extra traffic capacity on the busy corridor, and $500,000 for a wildlife fence along U.S. 6 between Heritage Road and 19th Street in Golden – to several in the $30 million and $40 million class.

Because of the lead time to get stimulus-funded projects underway, there are many projects this construction season that are being funded by the American Recovery and Reinvestment Act. They include the $47.2 construction of a new Central Park Boulevard interchange on Interstate 70 by SEMA Construction to provide better access to Denver’s Stapleton neighborhood and commercial area, the $17.9 million addition of a 17th Avenue interchange on Interstate 225 by Hamon Contractors to ease traffic flows into the Fitzsimons medical campus in Aurora, the $36.9 million replacement of the Alameda bridge over I-25 in Denver by Jalisco International and a new $32 million flyover ramp for southbound Santa Fe Drive to eastbound C-470 by Edward Kraemer and Sons in Littleton.

CDOT also will be starting up projects funded by the new revenue from the FASTER program’s vehicle registration fee hikes. They include new signals, auxiliary lane and realignment of the roadway geometry at the hazardous intersection of CO 7 and York Street in Adams County, more median cable guards on C-470 to prevent crossover head-on crashes and concrete median barrier on South Santa Fe Drive in Littleton.

“While a few large Recovery Act projects are still underway, there are many projects that are just starting that will greatly improve safety and mobility on our highway system,” said CDOT Executive Director Russell George. “Specifically, there will be several critical bridge and safety projects as a result of FASTER.”

Use this map of CDOT’s Region 6 — most of the Denver Metro area — along with the project descriptions below to see where these projects are located. I have put all 32 projects below with details on cost, schedule, work hours and project scope, along with pictures from many of them:

CDOT Traffic Watchers Spring 2010 Map
———————————————————
Metro Denver CDOT Projects Spring-Summer 2010
———————————————————
North Area (North Program Engineer John Schwab)
———————————————————

Edward Kraemer and Sons has placed girders at the new 120th Avenue bridge over US 36 has girders and will soon install bridge decking. CDOT photo.

Edward Kraemer and Sons has placed girders at the new 120th Avenue bridge over US 36 has girders and will soon install bridge decking. CDOT photo.

1. 120th Avenue Connection

Cost: $23.3 million

Contractor: Edward Kraemer and Sons, Inc.

Resident Engineer: Yet to be determined

Work: Constructs a new six-lane road across US 36 to connect 120th Avenue and State Highway 128 in Broomfield in order to provide greater connectivity to US 36 and local roadways. This project will construct two of the three phases needed to complete the entire project. As part of this project, a new bridge over US 36 will be constructed as well as a new bridge over Commerce Street. Several local roads such as Commerce Street, Old Wadsworth Boulevard and 118th Avenue will be realigned to correspond with the new roadway. The RTD park-n-Ride facility at Wadsworth Parkway will be relocated near the Broomfield Event Center. Currently, motorists in the Broomfield area can only cross US 36 at Wadsworth Parkway. Due to the lack of continuity with State Highway 128 and 120th Avenue, the US 36/Wadsworth Parkway interchange is heavily congested and State Highway 128 and 120th Avenue are operating at capacity during peak hours. Traffic forecasts indicate at least a doubling in traffic over the next 20 years. The new 120th Avenue Connection will provide relief on these major corridors by improving connectivity, safety and mobility.

Update: To date, crews have conducted embankment work on 120th Avenue and have begun bridge construction over US 36. Girders and bridge deck panels have been installed for the new bridge over US 36.

Work Hours: Single lane closures Sunday through Thursday from 8 p.m. to 5:30 a.m. with double lane closures from 10 p.m. to 5:30 a.m.

Duration: September 2009 through October 2010
———————————————————

Hamon Contractors is working on the middle segment of the new 104th Avenue bridge over I-25 in Northglenn. CDOT photo.

Hamon Contractors is working on the middle segment of the new 104th Avenue bridge over I-25 in Northglenn. CDOT photo.

2. 104th Avenue over I-25

Cost: $6.5 million

Contractor: Hamon Contractors, Inc.

Resident Engineer: Yet to be determined

Work: Replaces the 104th Avenue bridge over I-25, which was originally constructed in 1962 and is one of Colorado’s structurally deficient bridges. The new bridge will be wider to accommodate an additional left turn lane from eastbound 104th Avenue to northbound I-25.

Update: The new bridge is being constructed in three phases with work beginning on the northern portion. Currently, crews have completed the northern and middle portions of the new bridge and work will begin on the southern portion towards the end of April.

Work Hours:
I-25: Single lane closures Sunday through Thursday from 8 p.m. to 5:30 a.m. with double lane closures from 10 p.m. to 5:30 a.m. There will be occasional full closures of I-25 for girder installation, deck panel installation and bridge deck concrete pours.
104th Avenue: Single lane closures Monday through Friday from 8:30 a.m. to 3:30 p.m. with double lane closures Sunday through Thursday from 10 p.m. to 5:30 a.m. There will always one lane open in each direction.

Duration: May 2009 through January 2011
———————————————————

The original 80th Avenue bridge over U.S. 36 was built in 1951 as part of the Denver-Boulder Turnpike. Structures Inc. will build the replacement. CDOT photo.

The original 80th Avenue bridge over U.S. 36 was built in 1951 as part of the Denver-Boulder Turnpike. Structures Inc. will build the replacement. CDOT photo.

3. 80th Avenue over US 36

Cost: $7 million

Contractor: Structures, Inc.

Resident Engineer: Yet to be determined

Work: Replaces the 80th Avenue bridge over US 36, which was originally constructed in 1951 and is one of Colorado’s structurally deficient bridges. When complete, the bridge will be wider to accommodate an additional left turn lane from 80th Avenue to Oakwood Drive and a wider sidewalk. The project also realigns 80th Avenue to the east to improve sight distance, access and traffic flow. The improvements will accommodate the future widening of US 36 as determined through the US 36 Environmental Impact Statement.

Work Hours:
US 36: Single lane closures Sunday through Thursday from 10 p.m. to 5:30 a.m. There will be occasional full closures of US 36 for girder installation, bridge deck panel installation and bridge deck concrete pours.
80th Avenue: 80th Avenue will be closed for the duration of the project and a detour route will be in place which takes motorists to either 92nd Avenue on the north or 72nd Avenue on the south.

Duration: May 2010 through May 2011
———————————————————

SEMA Construction crews are nearing completion on new I-76 bridges over the South Platte River and CO 224 in Adams County. CDOT photo.

SEMA Construction crews are nearing completion on new I-76 bridges over the South Platte River and CO 224 in Adams County. CDOT photo.

4. I-76 over State Highway 224 and I-76 over the Union Pacific Railroad

Cost: $11 million (ARRA project)

Contractor: SEMA Construction, Inc.

Resident Engineer: Jake Koenig

Work: Replaces the existing I-76 structures over State Highway 224 and the Union Pacific Railroad, which were both originally built in 1967 and are two of Colorado’s structurally deficient bridges. In addition, the project will construct a crash wall for the I-76 structure over the Union Pacific Railroad as well for the State Highway 224 structure over the Union Pacific Railroad. The crash walls protect the bridge supports in case of a train derailment and are needed for the future North Metro FasTracks line. RTD is funding the design and construction of both walls.

Update: The bridges are being constructed in three phases as to not disrupt traffic. Currently, crews have completed the westbound and middle portions of the new bridges and are working on the eastbound portion. Girders have been installed for the final portion and crews will pour the bridge deck in late April.

Work Hours: Single lane closures Monday through Friday from 7 a.m. to 3:30 p.m. with occasional night work.

Duration: June 2009 through July 2010
———————————————————

The new CO 7 bridge being built by Zak Dirt Inc. over the South Platte River in Brighton is nearly complete. CDOT photo.

The new CO 7 bridge being built by Zak Dirt Inc. over the South Platte River in Brighton is nearly complete. CDOT photo.

5. State Highway 7 over the Platte River

Cost: $3.6 million

Contractor: Zak Dirt, Inc.

Resident Engineer: Jake Koenig

Work: Replaces the existing State Highway 7 structure over the Platte River with a new structure and replaces the existing bridge over the McCann Ditch with a new concrete box culvert. The State Highway 7 bridge over Platte River was originally constructed in 1967 and is one of Colorado’s structurally deficient bridges.

Update: To date, crews have completed two thirds of the new bridge and will have the final one third complete by the end of April. In May, crews will pave State Highway 7 in asphalt through the construction zone.

Work Hours: State Highway 7 is in a temporary alignment with traffic shifted to the south, but all lanes are open in each direction. Occasional night work will take place Sunday through Thursday from 9 p.m. to 5:30 a.m.

Duration: June 2009 through June 2010
———————————————————
6. 96th Avenue at I-76

Cost: $4.1 million (ARRA project)

Contractor: Castle Rock Construction Co.

Resident Engineer: Jake Koenig

Work: Constructs roundabouts at the on and off-ramps at the interchange of 96th Avenue and I-76 to improve safety and mobility.

Update: The majority of the work is now complete, but crews are finishing work in the southeast quadrant of the roundabouts.

Work Hours: Single-lane alternating traffic on 96th Avenue Monday through Friday from 7 a.m. to 5:30 p.m. The ramp from eastbound I-76 to 96th Avenue is closed as well as the southeast service road.

Duration: May 2009 through April 2010
———————————————————
7. US 6 over Lakewood Gulch

Quebec Street over Sand Creek

I-70 over I-25

Cost: $1.1 million

Contractor: Hamon Contractors, Inc.

Resident Engineer: Yet to be determined

Work: Repairs bridges at three locations in the Denver metro area. The work includes cleaning and repairing the culvert at US 6 over Lakewood Gulch; removing deteriorating concrete and patching at Quebec Street over Sand Creek; and replacing expansion joints on I-70 over I-25.

Update: The work on US 6 over Lakewood Gulch and Quebec Street over Sand Creek is complete. Crews will begin repairs at I-70 over I-25 in May once the expansion joints have been fabricated.

Work Hours: Single lane closures from 7 p.m. to 5:30 a.m., Sunday through Thursday.

Duration: February 2010 through June 2010
———————————————————
8. Colorado Boulevard (State Highway 2) – 62nd Avenue to Quebec Street

Cost: $3.2 million (ARRA project)

Contractor: LaFarge North America, Inc.

Resident Engineer: Bill McDonnell

Work: Resurfaces 2.4 miles of Colorado Boulevard in asphalt and upgrades traffic signals.

Work Hours: Single lane closures Monday through Friday from 7 a.m. to 4 p.m.

Duration: May 2010 through September 2010
———————————————————
9. US 85 at 144th Avenue

Cost: $800,000 (estimate)

Contractor: Yet to be determined

Resident Engineer: Bill McDonnell

Work: Constructs raised traffic islands on 144th Avenue to prohibit traffic in both directions of 144th Avenue from making left turns onto US 85 and also from crossing over US 85. Improvements will also be made to the left turn lanes on US 85.

Work Hours: Single lane closures Monday through Friday from 7 a.m. to 4 p.m. with occasional night work.

Duration: May 2010 through June 2010
———————————————————
10. State Highway 128 – McCaslin Boulevard to Eldorado Boulevard

Cost: $1.4 (estimate)

Contractor: Yet to be determined

Resident Engineer: Bill McDonnell

Work: Rotomills and resurfaces approximately one mile of SH 128 in asphalt

Work Hours: Single lane closures Monday through Friday from 9 a.m. to 4 p.m. with occasional night work.

Duration: August 2010 through September 2010
———————————————————
Central Area (Central Program Engineer Jim Bemelen)
———————————————————
11. I-70 at Ward Road

Cost: $8.5 million

Contractor: Asphalt Paving, Co.

Resident Engineer: Ed Martinez

Work: Reconstructs the eastbound I-70 exit ramps at 44th Avenue/Ward Road by moving the ramps east a quarter of a mile from their current location in order to increase merge distance. The north side of 44th Avenue will also be widened to accommodate two left turn lanes from eastbound 44th Avenue to I-70 as well as one full continuous merge lane on 44th Avenue between the I-70 off-ramp and Ward Road. Following the completion of interchange work, I-70 between Colfax Avenue and Kipling Street will be rotomilled and paved in asphalt.

Work Hours:
I-70: Single lane closures Monday through Friday from 9 a.m. to 2 p.m. and Sunday through Thursday from 7 p.m. to 5:30 a.m with double lane closures from 10 p.m. to 5:30 a.m.
44th Avenue: Lane closures Monday through Friday from 7 a.m. to 9 p.m. At least two left turn lanes from 44th Avenue to eastbound I-70 must remain open at all times as well as at least one lane of eastbound and westbound 44th Avenue.

Duration: January 2010 through June 2011
———————————————————
12. I-70 – Colorado Boulevard to Monaco Street

Cost: $5 million (estimate)

Contractor: Yet to be determined

Resident Engineer: Ed Martinez

Work: Replaces concrete barrier along I-70, constructs a new crash wall on Colorado Boulevard under I-70 and installs several new permanent sign structures.

Work Hours: Single lane closures Sunday through Thursday from 7 p.m. to 5:30 a.m. with double lane closures from 10 p.m. to 4 a.m.

Duration: June 2010 through October 2010
———————————————————
13. I-70 – Brighton Boulevard (State Highway 265) to Colorado Boulevard (State Highway 2)

Cost: $21.7 million

Contractor: American Civil Constructors, Inc.

Resident Engineer: Tony Stewart

Work: Repairs or replaces 60 expansion joints on the I-70 viaduct, which is over 40 years old. The project also reconstructs the median to improve drainage and replaces the bridge rail. In all, 64 expansion joints will be repaired or replaced on the viaduct between two projects. The first project, which was completed in 2006, repaired or replaced four expansion joints. This work will help extend the life of this aging structure, which was originally constructed in 1964.

Update: To date, crews have completed the majority of the expansion joint work between Brighton Boulevard and Vasquez Boulevard and have just started work between Vasquez Boulevard and Colorado Boulevard.

Work hours:
I-70: Single lane closures Sunday through Saturday from 8 p.m. to 5:30 a.m. with double lane closures from 10 p.m. to 5:30 a.m.
46th Avenue: Various segments of eastbound or westbound 46th Avenue will be closed based on the location of the work on I-70.

Duration: September 2008 through May 2011
———————————————————
14. Colorado Boulevard (State Highway 2) – Alameda Avenue to Martin Luther King Boulevard

Cost: $3.8 million

Contractor: LaFarge West, Inc.

Resident Engineer: Tony Stewart

Work: Resurfaces approximately 3.5 miles of Colorado Boulevard in asphalt, reconstructs the median and curb ramps. The traffic signals will be upgraded and turn lanes will be improved at the Colorado Boulevard/Colfax Avenue; Colorado Boulevard/17th Avenue and Colorado Boulevard/Montview Boulevard intersections.

Work hours: Single lane closures Monday through Friday from 8:30 a.m. to 3:30 p.m. and Sunday through Thursday from 9 p.m. to 5 a.m.

Duration: May 2010 through October 2010
———————————————————
15. I-70 at Central Park Boulevard

Cost: $47.2 million (ARRA project)

Contractor: SEMA Construction, Inc.

Resident Engineer: Tony Stewart

Work: Constructs a full interchange at I-70 and Central Park Boulevard which is between Havana Street and Quebec Street. The project will construct all ramps and structures for eastbound and westbound I-70 and for Central Park Boulevard. I-70 between Sand Creek and Havana Street will also be paved in asphalt. This project is being funded by the City and County of Denver with CDOT oversight.

Work Hours: Single lane closures Sunday through Thursday from 9 p.m. to 5:30 a.m. with double lane closures from 11 p.m. to 5:30 a.m. Occasional weekend work is possible.

Duration: June 2010 through Spring 2011
———————————————————
16. US 287 from 10th Avenue to Baseline Road (State Highway 7)

Cost: $5.9 million (estimate)

Contractor: Yet to be determined

Resident Engineer: Randy Furst

Work: Replaces approximately 230 concrete slabs, rotomills and paves two bridges on US 287 and conducts erosion control work on the east side of US 287.

Work Hours: Single lane closures Monday through Friday from 8:30 a.m. to 3:30 p.m.

Duration: May 2010 through December 2010
———————————————————
17. Federal Boulevard (US 287) at 120th Avenue (State Highway 128)
Sheridan Boulevard (State Highway 95) – 52nd Avenue to 56th Avenue

Cost: $664,000

Contractor: K.E.C.I Colorado, Inc.

Resident Engineer: Randy Furst

Work: Upgrades the traffic signals at both locations to include mast arm poles and LED lights. A raised median will also be installed on Sheridan Avenue between 52nd Avenue and 56th Avenue to improve safety

Work Hours: Single lane closures Monday through Friday from 8:30 a.m. to 3:30 p.m.

Duration: March 2010 through June 2010
———————————————————
South Area (South Program Engineer Paul Jesaitis)
———————————————————

Structures Inc. has excavation underway for the widening of Arapahoe Road under I-25. CDOT photo.

Structures Inc. has excavation underway for the widening of Arapahoe Road under I-25. CDOT photo.

18. Arapahoe Road (State Highway 88) – Yosemite Street to Boston/Clinton Street

Cost: $2.4 million

Contractor: Structures, Inc.

Resident Engineer: Abe Lavassani

Work: Adds an additional through lane in each direction by placing the new lanes where the existing on-ramp lanes exist. This means that the third lane will be separated from the existing through lanes by the pier columns. In addition, a turn lane on westbound Arapahoe Road between the southbound I-25 off-ramp and Yosemite Street will be added and the center median will be modified to accommodate the new configuration.

Update: The majority of the work has been completed, but median work and paving remain. Over the next couple of months, crews will remove the medians on eastbound and westbound Arapahoe Road, pave the additional lane from southbound I-25 to westbound Arapahoe Road, complete asphalt paving through the construction zone and complete landscaping.

Work Hours: Single lane closures Monday through Friday from 9 a.m. to 3:30 p.m. and Sunday through Thursday from 7:30 p.m. to 5:30 a.m. There will be occasional weekend work.

Duration: September 2009 through June 2010
———————————————————
19. Southbound I-25 to I-225
Parker Road (State Highway 83) to Southbound I-225

Cost: $1.5 million

Contractor: ABCO Construction, Inc.

Resident Engineer: Abe Lavassani

Work: Installs an anti-icing treatment on the ramps from southbound I-25 to northbound I-225 and northbound Parker Road to southbound I-225 to improve traction. Automatic anti-icing systems will also be installed on the ramp from southbound I-25 to northbound I-225 and from southbound I-225 to southbound I-25.

Update: The traction material has been installed on the ramp from southbound I-25 to northbound I-225 and on one lane of the ramp from northbound Parker Road to southbound I-225. Crews will likely return in May to complete the paving on the second lane of the northbound Parker Road to southbound I-225 ramp. Crews will be wrapping up the installation of the two anti-icing systems in the next couple of weeks.

Work Hours: Single lane closures Sunday through Thursday from 8 p.m. to 5:30 a.m. and from 9 p.m. Friday to 5 a.m. on Monday.

Duration: October 2009 through June 2010
———————————————————
20. Parker Road (State Highway 83) at Arapahoe Road (State Highway 88)

Cost: $30 million (estimate)

Contractor: Yet to be determined

Resident Engineer: Abe Lavassani

Work: The final phase of this interchange improvement project constructs a grade-separated interchange and the corresponding ramps and improves drainage. When complete, Parker Road will run over Arapahoe Road and the traffic signal will be removed for free-flowing traffic at the interchange.

Work Hours: Single lane closures Monday through Friday from 9 a.m. to 3:30 p.m. and Sunday through Thursday from 7 p.m. to 5:30 a.m. Throughout construction, Parker Road or Arapahoe Road may be placed in a temporary alignment.

Duration: May 2010 through December 2011
———————————————————
21. I-225 at Colfax Avenue (US 40)- Phase I

Cost: $1.4 million (ARRA project)

Contractor: Concrete Works of Colorado

Resident Engineer: Rick Erjavec

Work: This is the first phase of an interchange improvement project. This phase will reconstruct the southbound I-225 off-ramp to Colfax Avenue as well as the northbound I-225 on-ramp from Colfax Avenue. Drainage improvements will also be made. The City of Aurora will construct this phase with CDOT oversight.

Work Hours: Single lane closures Monday through Friday from 8:30 a.m. to 3:30 p.m. or Sunday through Thursday from 7 p.m. to 5:30 a.m.

Duration: November 2009 through April 2010
———————————————————
22. I-225 at Colfax Avenue (US 40)- Phase 2

Cost: $17.9 million (ARRA project)

Contractor: Hamon Contractors, Inc.

Resident Engineer: Rick Erjavec

Work: The second phase of the interchange improvement project will construct the southbound off-ramp to 17th Avenue and Colfax Avenue along with the southern portion of 17th Avenue to serve inbound traffic. The City of Aurora will construct this phase with CDOT oversight.

Work Hours: Single lane closures Monday through Friday from 8:30 a.m. to 3:30 p.m. or Sunday through Thursday from 7 p.m. to 5:30 a.m.

Duration: April 2010 through December 2011
———————————————————
23. I-225 – 2nd Avenue to Mississippi Avenue

Cost: $33 million (estimate)

Contractor: Yet to be determined

Resident Engineer: Rick Erjavec

Work: Widens I-225 between 2nd Avenue and Mississippi Avenue to accommodate three lanes in each direction with an additional auxiliary lane. I-225 from north of Colfax Avenue to 2nd Avenue will be restriped to also accommodate three lanes in each direction. A new 8-10 foot concrete noise wall will be constructed near Mississippi Avenue to replace the deteriorating wooden fence and a new 8-10 foot noise wall will be constructed near Potomac Circle.

Work Hours: Single lane closures Monday through Friday from 8:30 a.m. to 3:30 p.m. or Sunday through Thursday from 7 p.m. to 5:30 a.m.

Duration: June 2010 through August 2011
———————————————————

Castle Rock Construction crews continue to work on rehabilitation of the C-470 roadway. CDOT photo.

Castle Rock Construction crews continue to work on rehabilitation of the C-470 roadway. CDOT photo.

24. C-470 – I-25 to Santa Fe Drive (US 85)
C-470 Bike Trail – I-25 to I-70

Cost: $32 million (ARRA project)

Contractor: Castle Rock Construction Co.

Resident Engineer: Ron Buck

Work: Repairs or replaces concrete slabs along nine miles of C-470 and resurfaces C-470 in asphalt. Rehabilitates and replaces concrete slabs on the C-470 bicycle/pedestrian trail.

Update: To date, the concrete repairs are complete on westbound C-470 and the majority of eastbound C-470. Crews will complete the concrete work on eastbound C-470 in the coming months and then begin asphalt paving on both eastbound and westbound C-470. Bike path work is also still underway.

Work Hours: The majority of the roadway work on C-470 will take place from 8 p.m. Friday to 5 a.m. Monday each weekend. Single lane closures are also possible Monday through Friday from 8:30 a.m. to 3:30 p.m. and Sunday through Thursday from 7 p.m. to 5:30 a.m. Work on the bike path will take place Monday through Friday from 8:30 a.m. to 5 p.m.

Duration: July 2009 through September 2010
———————————————————

The 1958 Valley Highway bridge over Alameda Avenue -- and the flash flooding that often occurs underneath it -- will be things of the past with a replacement project now getting underway by Jalisco International. CDOT photo.

The 1958 Valley Highway bridge over Alameda Avenue — and the flash flooding that often occurs underneath it — will be things of the past with a replacement project now getting underway by Jalisco International. CDOT photo.

25. I-25 at Alameda Avenue

Cost: $36.9 million (ARRA project)

Contractor: Jalisco International, Inc.

Resident Engineer: Ron Buck

Work: Replaces the Alameda Avenue bridge over I-25 with one that is wider to accommodate an additional lane in each direction. Minor improvements will also be made to I-25 under Alameda Avenue and drainage will be improved. This work is part of a larger project that will eventually improve I-25 as determined in the I-25 Valley Highway Environmental Impact Statement.

Work Hours: Single lane closures Sunday through Thursday from 8 p.m. to 5 a.m. with occasional weekend work.

Duration: April 2010 through September 2011
———————————————————
26. Santa Fe Drive (US 85) at C-470

Cost: $32 million (ARRA project)

Contractor: Edward Kraemer & Sons, Inc.

Resident Engineer: Ron Buck

Work: Constructs a flyover ramp from southbound Santa Fe Drive to eastbound C-470 to improve safety and mobility.

Work Hours:
Santa Fe Drive: Single lane closures Monday through Friday from 8:30 a.m. to 3:30 p.m. and Sunday through Thursday from 8 p.m. to 5:30 a.m.
C-470: Single lane closures Sunday through Thursday from 8 p.m. to 5:30 a.m. Full closures of C-470 will also be required for girder installation, bridge deck panel installation and concrete deck pour.

Duration: June 2010 through January 2012
———————————————————
27. I-25 – 6th Avenue to 23rd Avenue

Cost: $4.3 million (ARRA project)

Contractor: Brannan Sand and Gravel Co.

Resident Engineer: Tony Gross

Work: Rotomills and resurfaces approximately three miles of I-25 in asphalt.

Update: The majority of work is complete, but crews need to complete some smoothness grinding and some erosion control work.

Work Hours: Single lane closures Sunday through Thursday from 8 p.m. to 5 a.m.

Duration: June 2009 through April 2010
———————————————————

Concrete Express crews excavate for new bridge pier footings at the Hampden Avenue bridge over Federal Boulevard. CDOT photo.

Concrete Express crews excavate for new bridge pier footings at the Hampden Avenue bridge over Federal Boulevard. CDOT photo.

28. Hampden Avenue (US 285) -Kipling Street to Federal Boulevard

Cost: $40.1 million

Contractor: Concrete Express, Inc.

Resident Engineer: Tony Gross

Work: Replaces the Wadsworth Boulevard (State Highway 121), Pierce Street and Federal Boulevard (State Highway 88) bridges over Hampden Avenue and reconstructs Hampden Avenue between Wadsworth Boulevard and Federal Boulevard.

Update: Construction started near Federal Boulevard with crews realigning Hampden Avenue to accommodate reconstruction in the median. In late April/early May, construction will begin to replace the Hampden Avenue bridge over Federal Boulevard. Construction will continue to move west as work progresses.

Work Hours: Single lane closures Monday through Friday from 8:30 a.m. to 3:30 p.m. and Sunday through Thursday from 7 p.m. to 5:30 a.m. Full closures of Hampden Avenue will also be required for girder installation, bridge deck panel installation and concrete deck pour.

Duration: January 2010 through June 2011

Region 6 Traffic Engineering Projects (Traffic Engineer Steve Hersey)
———————————————————
29. State Highway 7 at York Street

Cost: $750,000 (estimate)

Contractor: Yet to be determined

Resident Engineer: Jake Koenig

Work: Adds an auxiliary lane on State Highway 7 from 168th Avenue to York Street and installs a new traffic signal at the SH 7/York Street intersection.

Work Hours: Single lane closures Monday through Friday from 8:30 a.m. to 3:30 p.m.

Duration: June 2010 through November 2010
———————————————————
30. C-470 – Quebec Street to I-25
C-470 – Morrison Road to Wadsworth Boulevard
Santa Fe Drive (US 85)- Aspen Grove Way to Ridge Road

Cost: $3.3 million (estimate)

Contractor: Yet to be determined

Resident Engineer: Leela Rajasekar

Work: Installs median cable guardrail in two locations along C-470 to help prevent crossover accidents. Concrete median barrier will also be installed on Santa Fe Drive.

Work Hours: Single lane closures Sunday through Thursday from 8 p.m. to 5 a.m.

Duration: June 2010 through February 2011
———————————————————
31. US 6 – Heritage Road to 19th Avenue

Cost: $500,000 (estimate)

Contractor: Yet to be determined

Resident Engineer: Leela Rajasekar

Work: Installs a wildlife fence along US 6 to help prevent wildlife/vehicle collisions.

Work Hours: Single lane closures Monday through Friday from 8:30 a.m. to 3:30 p.m. and Sunday through
Thursday from 7 p.m. to 5:30 a.m.

Duration: August 2010 through November 2010
———————————————————
32. Parker Road (State Highway 83) – Belleview Avenue to Hampden Avenue

Cost: $180,000 (estimate)

Contractor: Yet to be determined

Resident Engineer: Alazar Tesfaye

Work: Restripes Parker Road to accommodate a third through lane in each direction.

Work Hours: Sunday through Thursday from 8 p.m. to 5:30 a.m.

Duration: May 2010 through June 2010

Kevin Flynn

More Transportation News from Kevin Flynn's Inside Lane

Get on the Inside Lane with longtime journalist Kevin Flynn, and get more news and views on Colorado's transportation system than you can get anywhere else. Slower traffic keep to the right, we're on the Inside Lane!
Visit Kevin Flynn's Inside Lane

Speak Your Mind

Tell us what you're thinking...
and oh, if you want a pic to show with your comment, go get a gravatar!